Maumee Indoor Progress
August 4, 2003

Back wall still
intact.
Front as it has appeared for years.
Marquee as it has appeared.
August 7, 2003

Back wall removed.
August 27, 2003

Basement being dug for the new addition on back of
Theater.
North side of building - footers
poured for new addition.
From lobby looking into
Theater.
Stage area with back wall
gone.
In theater looking back towards old restrooms (upstairs) and projection room.
September, 2003

Inside lobby, south wall facing the old
Anthony
Behind Theater, new basement walls and elevator
Wayne Barber
Shop.
being constructed.
October 2003
Taken from on top of the Sophia Street Water Tower on October 10, 2003.
Note the large
addition on back and side of the theater, repairs to the roof near the marquee,
and the
construction of the parking lot across Conant Street.

October 27, 2003 - New addition on William Street
side