Maumee Indoor Progress
August 4, 2003

       
Back wall still intact.                             Front as it has appeared for years.        Marquee as it has appeared.

August 7, 2003

    
Back wall removed.

August 27, 2003

       
Basement being dug for the new addition on back of Theater.                              North side of building - footers
                                                                                                                            poured for new addition.
          
 From lobby looking into Theater.                                 Stage area with back wall gone.                                          

 

In theater looking back towards old restrooms (upstairs) and projection room. 

 

 

 

 

September, 2003

      

Inside lobby, south wall facing the old Anthony                         Behind Theater, new basement walls and elevator
Wayne Barber Shop.                                                               being constructed.

October 2003

   
Taken from on top of the Sophia Street Water Tower on October 10, 2003.  Note the large
addition on back and side of the theater, repairs to the roof near the marquee, and the
construction of the parking lot across Conant Street.

 

       
October 27, 2003 - New addition on William Street side